Press Release: Jordon Cove LNG Pipeline Project DEAD

December 1, 2021 — Pembina, the Canadian company that tried to impose a fracked gas pipeline and export terminal on communities across Southern Oregon, today filed a formal request asking the Federal Energy Regulatory Commission (FERC) to cancel its permit for the project.

Federal Energy Regulatory Commission Upholds Oregon’s Denial of Key Jordan Cove LNG Permit

January 19, 2021 — Today, the Federal Energy Regulatory Commission (FERC) upheld the Oregon Department of Environmental Quality’s denial of a key permit for the proposed Jordan Cove LNG export terminal and Pacific Connector fracked gas pipeline. The Jordan Cove LNG project cannot move forward without a Clean Water Act approval from the state of Oregon.

BLOG: Field Checking Old-Growth on the Jordan Cove LNG Pipeline Path

By Sam Krop, Cascadia Wildlands Grassroots Organizer In the midst of the COVID-19 pandemic, we spent the weekend field checking a threatened area of old growth forest along the proposed Jordan Cove pipeline route out in the Oregon coast range between the towns of Remote and Sitkum, by Coquille. As we drove along the coast … Read more

Press Release: Oregonians Demand Rehearing of Pipeline Project Approval

April 20, 2020 — Today, the Klamath Tribes, impacted landowners, and over 25 public interest organizations submitted a joint request for rehearing to the Federal Energy Regulatory Commission (FERC) on its decision to conditionally approve the Jordan Cove LNG export terminal and Pacific Connector fracked gas pipeline. The broad coalition’s rehearing request challenges FERC’s imbalanced and inadequate review of the Jordan Cove LNG proposal.

Organizations opposing Jordan Cove LNG thank Oregon leaders

March 25, 2020 — Despite the ongoing COVID-19 public health crisis, on Thursday, March 19 a politically unbalanced Federal Energy Regulatory Commission (FERC) approved the Jordan Cove Energy Project and Pacific Connector Gas Pipeline over the objections of numerous state, federal, and local stakeholders and decision makers (details here.)

Despite Permit Denials and Current Public Health Crisis, Federal Agency Approves Jordan Cove LNG

March 19, 2020 — In the midst of the global coronavirus pandemic and national health emergency, the Federal Energy Regulatory Commission (FERC) conditionally approved the Jordan Cove LNG export terminal and Pacific Connector fracked gas pipeline today. The approval is conditioned on Pembina, the Canadian fossil fuel corporation behind the project, qualifying for critical permits from the state of Oregon, three of which have already been denied or withdrawn.

FERC Votes 2-1 to Not Move Fracked Gas Pipeline Forward!

February 20, 2020 — On the heals of yesterday’s State of Oregon denial of yet another necessary permit for the Jordan Cove LNG Project, the Federal Energy Regulatory Commission (FERC) this morning voted 2-1 to delay the Trump administration’s approval process.

Jordan Cove Withdraws Removal Fill Application!

January 24, 2020 — Amidst enormous public opposition and just one week before the Department of State Lands (DSL) was set to make a decision on a critical Removal-Fill permit on the Jordan Cove LNG export terminal and Pacific Connector fracked gas pipeline, Pembina has withdrawn their application to the agency.

Press Release: Critical Jordan Cove LNG Permit Denied by Oregon

May 6, 2019 — The Oregon Department of Environmental Quality (DEQ) today delivered a potentially fatal blow to the Jordan Cove LNG project and the Pacific Connector fracked gas pipeline which has faced fierce opposition for more than a decade by a grassroots coalition of impacted landowners, anglers, small business owners, tribal members, health professionals, and many more Oregonians and Northern Californians.

Join Us for a Rally Against the Fracked Gas Pipeline – January 15, 2019

Cascadia Wildlands is teaming up with 13 other organizations to coordinate a rally in opposition of the Jordan Cove Energy Project.  If built, this LNG/Fracked Gas Pipeline and Export Facility would harm nearly 500 waterways (100,000+ public drinking water), seize property from private landowners through eminent domain, create major safety and public health hazards, impact … Read more

A Report Back on Field Checking the Proposed Jordan Cove LNG Terminal

by Sam Krop, Cascadia Wildlands’ Grassroots Organizer August 2, 2018 On a spotless, windy morning on July 1, over 50 concerned citizens gathered around a boat launch on the North Spit of Coos Bay to explore the place that would be most impacted by the construction of the proposed Jordan Cove liquefied natural gas export … Read more